Project Description

Sungun Phase III Copper Concentration Plant

Sungun Phase III contract was awarded to KMP as consultant on Sep 23rd, 2019. The main responsibilities of Consultant are Preliminary studies , Conceptual & Basic Design, Preparing Tender Document, Evaluation of Contractors, Detail Design Review and Approval, Field Engineering Supervision, TBEs Review and Approval, Monitoring the Manufacturers & Suppliers and Project Controlling.

Project Main Aspects

  • Preliminary studies
  • Conceptual & Basic Design
  • Preparing Tender Document
  • Evaluation of Contractors
  • Detail Design Review and Approval
  • Field Engineering Supervision
  • TBEs Review and Approval
  • Monitoring the Manufacturers & Suppliers
  • Project Controlling

Project Highlights

  • Changing the Stock Pile Location because of rock slope instability
  • Increasing the Stockpile capacity with designing ring wall due to area limitations
  • Designing the Stockpile with roof structure for avoiding dust dispersion
  • Optimizing infra-structure of two phases of 7 and 12 MTPY by merging same units such as Stockpile , industrial, Semi-Industrial and non-industrial buildings
  • Minimizing the risk of land sliding along the Overland conveyor route by using tunnel
  • Optimizing the level of the Crusher platform in order to eliminate the risks of flood in the area of the Sacrificial transfer tower
  • Using mechanical frame in order to minimize using of huge trestles, excavations, concrete works and using topography for achieving to foresighted project time and cost

Project Details

DATE

September 23th, 2019

CLIENT

National Iranian Copper Industries Co. (NICICO)

MINE and PLANT CAPACITY

7 MTPA Feed

150000 MTPA Cu Concentrate

CONTRACTOR

Kayson

LOCATION

Sungon, Tabriz, IRAN

Project Gallery